Revision of the General Staff of the Turkish Armed Forces and the Ministry of National Defense (MoND) Headquarters System

The existing electrical infrastructure of all buildings within the General Staff and MoND Headquarters were replaced with a main step-down transformer, which regulates potential voltage drops in the city network. Additionally, a main transformer building was established by installing generators that activate during power outages. Five power transformers, one of which is buried in the ground, were installed in the headquarters, their ring connections to each other were established, and the entire system was automated with SCADA. In addition, the building’s main distribution panel, floor panels and room tables were installed. An installation gallery, which includes the main cables for all electrical equipment and the pipes, was built.

Employer: Department of Defense
Location: Ankara/TURKEY

GALERİ